Blessed Kateri Construction Diary

Construction Pg 2 Construction Pg 3 Construction Pg 4 Construction Pg 5 Construction Pg 6 Construction Pg 7 Construction Pg 8 Construction Pg 9 Construction Pg 10

Update from Ola Ostlund-Project Manager  May 26, 2007
We are progressing at a steady pace, and with some minor stumbling blocks out of the way, we are now close to starting the main excavation. Re-routing of the water, sewer and fire water is close to being completed. In the last couple of weeks the following are the tasks that have been completed or are in progress:
Installation of shoring piles. Demolition of part of site wall. Re-routing and replacement of domestic water lines, sewer and fire water. For the next coming weeks the following will be started:
Excavation and export of soil. Installation of shoring piles for new office building.
Start of footings for walls and pads. Thank you all for not parking in the Fire Lanes.
If you have any questions or comments feel free to contact me directly. Many parishioners are assisting with advice and comments and we encourage your involvement. After all, our Church is Yours and God’s House.
Let’s build GOD’S house!


June 13, 2007

Dear Parishioners and friends of Blessed Kateri Tekakwitha Catholic Church,

The foundation work is in full progress. Shortly we will are ready to for the first placement of Concrete. In a couple of weeks you will see the first pieces of steel being erected. Utilities are being installed in the basement area. In the last couple of weeks the following are the tasks that have been completed or are in progress:

• Installation of shoring piles for Administrative Building.
• Re-compaction for the basements.
• Finish grading at the basements.
• Start of footings for walls and pads.

For the next coming weeks the following will be started.

• Underground utility installations at the basements.
• Complete excavation for wall and pad footings.
• Install rebar for wall and pad footings.
• Place concrete for grade beams and footings.
• Erect basement steel columns.
• Start placement of Structural Masonry.

If you have any questions or comments feel free to contact me directly. Many parishioners are assisting with advice and comments and we encourage your involvement. After all, our Church is Yours and God’s House.
Let’s build GOD’S house.

Ola Ostlund
Project Manager
 

Msgr. Mike helping out

June 27, 2007

Dear Parishioners and friends of Blessed Kateri Tekakwitha Catholic Church,

It is now time for the first placement of Concrete for the foundations. Some off site tasks are getting ready to start such as Steel Fabrication. In the last couple of weeks the following are the tasks that have been completed or are in progress:

• Start of footings for walls and pads.
• Underground utility installations at the basements.
• Complete excavation for wall and pad footings.
• Install rebar for wall and pad footings.

For the next coming weeks the following will be started.

• Place concrete for grade beams and footings.
• Erect basement steel columns.
• Start placement of Structural Masonry.

If you have any questions or comments feel free to contact me directly. Many parishioners are assisting with advice and comments and we encourage your involvement. After all, our Church is Yours and God’s House.
Let’s build GOD’S house.

Ola Ostlund
Project Manager
oostlund@ocim.com

June 30,2007  -  Days before 1st concrete pour

notice the similarities of shape beginning to appear!  yay

Click for Other New Church Renderings